Abstract
The northwest region of Bangladesh is divided into four geomorphological units which show different flood features. The region has suffered severe flood damage both in 1987 and 1988. After these floods Bangladesh Action Plan for Flood Control was established by the World Bank. In the northwest region the plan proposed two major projects, namely, an interceptor drain and a diversion channel. A Polder Project is also going on in this region. However these major projects are mainly on structural methods and require much cost for long embankments. The author suggests smaller but reasonable projects combining structural and non-structural methods in the region.
Original language | English |
---|---|
Pages (from-to) | 313-318 |
Number of pages | 6 |
Journal | GeoJournal |
Volume | 31 |
Issue number | 4 |
DOIs | |
Publication status | Published - 1993 Dec |
ASJC Scopus subject areas
- Geography, Planning and Development