TY - JOUR
T1 - Update of YOKOHAMA HTS cable project
AU - Yumura, Hiroyasu
AU - Ashibe, Yuichi
AU - Ohya, Masayoshi
AU - Itoh, Hideki
AU - Watanabe, Michihiko
AU - Masuda, Takato
AU - Ichikawa, Hiroshi
AU - Mimura, Tomoo
AU - Honjo, Shoichi
AU - Hara, Tsukushi
AU - Ohno, Ryusuke
AU - Shimoda, Masahiro
AU - Nakamura, Naoko
AU - Komagome, Toshihiro
AU - Yaguchi, Hiroharu
PY - 2013
Y1 - 2013
N2 - The high-temperature superconducting (HTS) cable demonstration project supported by Ministry of Economy, Trade and Industry and New Energy and Industrial Technology Development Organization has started in Japan. The target of this project is to operate a 66 kV, 200 MVA HTS cable in the live network of Tokyo Electric Power Company in order to demonstrate its reliability and stable operation. The design of the HTS cable with DI-BSCCO has been completed as well as those of a termination and a joint. A 30-m HTS cable system with terminations, a splice, and a cooling system was installed in the SEI facility and confirmed the cable has good performances as design. The HTS cable, splice box, and termination vessels have been manufactured with the same design of a 30-m cable system. By now, the HTS cables have been installed into the conduit at the Asahi substation of Tokyo Electric Power Company. The constructions of splice and terminations have been completed. The HTS cable system at Asahi substation was cooled down in this spring. This paper describes the design and completion test results of the HTS cable system.
AB - The high-temperature superconducting (HTS) cable demonstration project supported by Ministry of Economy, Trade and Industry and New Energy and Industrial Technology Development Organization has started in Japan. The target of this project is to operate a 66 kV, 200 MVA HTS cable in the live network of Tokyo Electric Power Company in order to demonstrate its reliability and stable operation. The design of the HTS cable with DI-BSCCO has been completed as well as those of a termination and a joint. A 30-m HTS cable system with terminations, a splice, and a cooling system was installed in the SEI facility and confirmed the cable has good performances as design. The HTS cable, splice box, and termination vessels have been manufactured with the same design of a 30-m cable system. By now, the HTS cables have been installed into the conduit at the Asahi substation of Tokyo Electric Power Company. The constructions of splice and terminations have been completed. The HTS cable system at Asahi substation was cooled down in this spring. This paper describes the design and completion test results of the HTS cable system.
KW - High-temperature superconductors
KW - power cable installation
KW - power cable joint
KW - superconducting power cables
UR - http://www.scopus.com/inward/record.url?scp=84875776376&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84875776376&partnerID=8YFLogxK
U2 - 10.1109/TASC.2013.2245931
DO - 10.1109/TASC.2013.2245931
M3 - Article
AN - SCOPUS:84875776376
SN - 1051-8223
VL - 23
JO - IEEE Transactions on Applied Superconductivity
JF - IEEE Transactions on Applied Superconductivity
IS - 3
M1 - 6458991
ER -